📞 Contact UsHomeProductsCatalogueApplicationsProjectsMarketsBlog🎬 VideosTools💰 CalculatorAbout

FRP Grating Landed Cost: What Actually Adds Up

Cost Structure
Direct Answer

Landed cost is FOB plus freight, duty, inland transport, clips and documentation; on a typical container the panel itself is 55-70% of the total and freight is the second largest line.

  • Biggest lever: container loading, because freight is volume-driven
  • Hidden line: clips and edge trim, 2-5% and often left out of the quote
  • Key spec: ask every supplier for a landed-cost table, not an FOB number

The invoice price is the smallest part of what a deck costs. This is the arithmetic behind a delivered square metre of FRP grating.

What Does Delivered FRP Grating Actually Cost?

Landed cost is FOB plus freight, duty, inland transport, clips and documentation; on a typical container the panel itself is 55-70% of the total and freight is the second largest line. The invoice price is the smallest part of what a deck costs. This is the arithmetic behind a delivered square metre of FRP grating.

In this guide: ex-works basis, what moves the unit price, freight by volume, duty and clearance, accessories, cutouts and fabrication, packaging, site handling, and the total. The practical test of a quotation is whether it separates those lines. A single delivered number cannot be checked, cannot be compared, and usually contains a margin for the lines the supplier has guessed. Ask for the breakdown, then compare the parts that should be similar across suppliers and interrogate the parts that are not. The cheapest single number is almost never the cheapest delivered square metre, because the lines it has hidden are the ones that surprise you at the port.

Pultruded FRP grating panels packed for export shipment

The Six Lines That Make Up the Landed Cost

Every landed cost calculation starts with the ex-works unit price, because that is the only figure the factory controls. Everything above it is logistics, duty and handling, and those lines behave differently: freight scales with volume rather than value, duty scales with value, and handling scales with how the panels are packed. Buyers who compare only the delivered number cannot see which of those three is out of line, and they usually conclude the factory is expensive when the freight forwarder is.

The table below gives the typical share of each line on a full container of standard panels. Treat the percentages as ranges, not as quotes: a part container shifts freight up, a high-duty market shifts duty up, and a fabricated deck shifts accessories and fabrication up. The point of the table is to show which line to interrogate, not to price your project. When two suppliers come back with the same delivered number, the one who can show the six lines separately is the one you can trust; the one who gives a single figure has bundled the unknowns into a margin.

ComponentTypical shareMain driver
FOB panel price55-70%Section, mesh, resin, order size
Sea freight10-25%Volume, container utilisation, route
Duty and VAT0-15%HS code and destination country
Inland transport3-8%Distance, unloading equipment
Clips and accessories2-5%Clip count per panel edge
Inspection and documents1-3%Third-party inspection, certificates

What Moves the Ex-Works Unit Price

Four decisions set the ex-works price before any negotiation: resin, section, surface and quantity. Vinyl ester costs more than isophthalic polyester. A 50 mm pultruded bar costs more per square metre than a 38 mm one because there is more glass and resin in it. Grit surface adds a process step. And a 200 m2 order carries setup and colour costs that a 2,000 m2 order spreads across more panels.

Open area is the quiet variable. Going from 40% to 60% open removes material, so the panel gets lighter and cheaper per square metre while carrying less load, a saving that reappears as a cost if the deck then needs a mid bearer. The 38 mm molded panel at 19.5 kg/m2 is the default specification in most of our orders; a 50 mm pultruded panel carries more load but costs more, and a 25 mm molded panel is cheaper but only fits short spans. Pick the section to the load table, not to the price list, because a panel that is one size too light shows up as a deflection complaint on the first wet day, long after the savings were celebrated.

Freight Is a Volume Problem, Not a Weight Problem

FRP grating is light and bulky, so containers cube out long before they weigh out. A 40 ft container may take around 60 to 70 m2 of standard panels depending on panel size and stacking, and the freight cost per square metre falls as the container fills. That is why a small order can look disproportionately expensive: the same fixed container cost is spread over fewer square metres.

Panel size drives this directly. Standard 1220 x 3660 mm panels pack more efficiently than short cut lengths, because short lengths leave void space. If the deck allows standard panels with site cuts, freight per square metre drops, and the cut edges are sealed on site rather than in the factory. Filling the container is the single biggest lever on the freight line: a half-empty box costs almost as much as a full one, and the per-square-metre freight on the half box is nearly double. Stage the order to fill the box rather than shipping a partial lot. If the project phasing forces a partial shipment, ask the forwarder for a groupage rate rather than accepting a full-box quote; groupage is cheaper on a small volume and it keeps the per-square-metre freight honest.

Duty, Clearance and the Origin Documents

Duty depends on the tariff code applied to glass-fibre reinforced plastic grating in the destination country, and on the origin documentation. Rates differ by market and change with trade measures, so the figure has to be checked for the specific destination rather than assumed. A CIF price without the duty line is not a delivered price, and a DAP quote that omits the destination duty is a quote that will be corrected on the first invoice.

Clearance costs are real but secondary: brokerage, terminal handling, and the port charges that appear on the forwarder invoice rather than the factory invoice. Ask for them as a separate line so they do not hide inside a freight rate. We ship with a packing list, commercial invoice, certificate of origin, resin batch certificates, the load table for the supplied section and installation instructions, which is the document set most customs authorities expect for an FRP grating consignment. Ask for the document list in the RFQ so nothing is missing when the container arrives, because a missing certificate of origin is the most common reason a consignment sits in the port for an extra week.

Accessories, Cutouts, Packaging and Site Handling

Clips, bolts and washers are not free, and their quantity is set by the deck rather than by taste. A 1,000 m2 deck at 10 clips per square metre is 10,000 clips, which is a material line in its own right, and it usually arrives as a surprise after the grating has been ordered. The same applies to handrail, nosing, frame and cut edge sealant. Each is a small unit price multiplied by a large quantity, and each is cheaper to include in the original enquiry than to air-freight later.

A panel with penetrations, notches and a nosing is no longer a stock panel. It is fabricated, which means labour, sealant and a higher scrap rate. On a deck with many openings the fabrication line can rival the freight line. Ask for the cutout count on the quotation. Panels ship in bundles or crates, and both cost money: timber, strapping, labour, and the extra volume the crate takes in the container. At site a 1220 x 3660 mm panel is a two-person lift; a 6 m panel needs a spreader and a machine. If the site has no forklift, the crane that lifts the deck belongs in the landed cost.

Ask for the cutout count on the quotation. A supplier who prices per panel without knowing the cutouts has priced a different product, and the difference surfaces at the invoice.

At site the cost moves again. A 1220 x 3660 mm panel is a two-person lift; a 6 m panel needs a spreader and a machine. If the site has no forklift, the crane that lifts the deck belongs in the landed cost, not in the installation budget discovered later.

Building the Total and Choosing the Supplier

Landed cost per square metre equals ex-works unit price, plus fabrication for cutouts and edges, plus accessories, plus packaging, plus inland transport to port, plus ocean or road freight, plus insurance, plus duty and clearance, plus delivery to site, plus site handling. Each line is real and each line is quotable. Can I reduce landed cost without reducing quality? Yes: use standard panel sizes where the deck allows, fill the container, and bundle accessories with the grating order instead of shipping them later.

We manufacture at a 20,000 m2+ plant with 200+ staff, export to 40+ countries, hold MOQ 10 m2 and a 12-36 working day lead time from a confirmed drawing. Oversized panels, custom colours, new moulds and specialty resins are quoted with a separately confirmed schedule. We will quote a landed-cost table with every line separated, and we will price clips, edge trim and cutouts on the same quotation rather than as a later surprise. Send us the panel schedule, the destination port and the Incoterm you want, and we will come back with the breakdown rather than a single FOB number that hides the freight and duty inside a margin.

Frequently Asked Questions

What is included in landed cost?
Ex-works price, fabrication, accessories, packaging, inland transport, ocean freight, insurance, duty and clearance, delivery to site and site handling. Each should be a separate line, and on a full container the panel itself is 55-70% of the total.
Why is freight per square metre higher on small orders?
Because a container has a fixed cost and grating is bulky. A 40 ft box takes about 60-70 m2 of standard panels, and a part load spreads the same container cost over fewer square metres. Filling the box is the biggest lever.
Does higher open area reduce the price?
It reduces material and therefore the unit price, but it also reduces capacity, which can force an extra bearer. Compare the installed deck, not the panel: a 60% open panel at 18 kg/m2 may need a mid bearer that erases the saving.
Are clips usually in the grating price?
Rarely. Clips and bolts are a separate line and their quantity is set by span and uplift, typically around 10 per square metre on a 1,000 m2 deck. Ask for the clip count in the same quotation.
How much does duty add?
It depends on the HS code and origin for the destination market and changes with trade measures, so it has to be checked for the specific country rather than estimated. Expect 0-15% of the CIF value, and ask for it as a separate line.
Can I reduce landed cost without reducing quality?
Yes: use standard 1220 x 3660 mm panels where the deck allows, fill the container, and bundle accessories with the grating order instead of shipping them later. Stage the order so the box is full rather than partial.
ZEALL Engineer

FRP Grating Technical Team

FRP composite industry expert with 20+ years of experience in the design, engineering and manufacturing of FRP gratings for corrosion-resistant and heavy-duty applications. Published by NANTONG ZEALL NEW MATERIALS CO., LTD.

Published: 2026-09-09 |Category: Cost Structure|Author: FRP Grating Technical Team
Have Questions? Contact Us →
Previous Article
FRP vs Steel Grating: Which Costs Less?

Document Preview

Preview mode · For full document, click Download

Download Document

Thank you for your interest. Please fill in your email and company name. Our technical and sales team will contact you within 30 minutes (during working hours) to provide support!

📧 Your information will be sent to [email protected]. We respect your privacy and will never share your data.

Thank You!

Your request has been received successfully.

Our technical and sales team will contact you within 30 minutes (during working hours) to provide the document and professional support!

If you need urgent assistance, please email: [email protected]